Writing a system integration plan
Integrate in the order the dependencies allow, test each step, and never add two unknowns at once.
Assumptions: A practical template based on the NASA Systems Engineering Handbook; not a standard. All numbers in the example are illustrative and the code is executed by the site’s tests.
1. Engineering problem
Bringing every subsystem together at once makes a failure impossible to localise. A plan integrates in dependency order, with a test after each step, so a failure points to the last thing added.
2. When is this needed?
- After interfaces are defined and before hardware arrives.
- When a new subsystem is added to a working robot.
- Before a field trial.
3. Selection and design decisions
| Plan element | Content |
|---|---|
| Order | Dependency order: drivers, frames, safety, state estimation, mapping, navigation |
| Entry criteria | What must be true before the step starts (inputs available, previous step passed) |
| Exit criteria | A measurable check (rate, latency, error, recorded bag) that the step passed |
| Test environment | Bench, simulation, test area, field |
| Risks and fallbacks | What could go wrong and the fallback (stub, recorded data, simulation) |
| Owner and date | One person per step |
4. Advantages and disadvantages
- Big-bang integration is fast on paper and slow in practice; incremental costs planning and finds problems earlier.
- Simulation first is cheap and does not reveal timing or electrical issues.
- Stubs and recorded data let parallel teams proceed before all hardware exists.
5. Requirements and constraints
- A step starts only when its dependencies have passed their exit criteria.
- Each exit criterion is a number or a pass/fail test, not “looks fine”.
- Cycles in the dependency graph are design errors to resolve (an interface to split).
6. Architecture
drivers ─▶ tf ─▶ imu_fusion ─▶ slam ─▶ nav
└─▶ safety (parallel with tf)7. Implementation
- List the subsystems and what each depends on.
- Compute the order (below); steps in the same level can run in parallel.
- Write entry and exit criteria for each step from the requirements.
- Name the stubs or recorded data used where a dependency is missing.
- Record results after each step and update the plan.
deps = {"drivers": [], "tf": ["drivers"], "imu_fusion": ["drivers", "tf"], "slam": ["imu_fusion"], "nav": ["slam", "tf"], "safety": ["drivers"]}
done, order = set(), []
while len(done) < len(deps):
ready = sorted(n for n, d in deps.items() if n not in done and all(x in done for x in d))
if not ready:
raise SystemExit("cycle in the dependency graph")
order.append(ready)
done.update(ready)
for i, level in enumerate(order, 1):
print(i, level)Printed (checked by the site’s tests):
1 ['drivers']
2 ['safety', 'tf']
3 ['imu_fusion']
4 ['slam']
5 ['nav']Reading it: drivers come first; the safety function and the transform tree are independent of each other and can be integrated in parallel; state estimation needs both drivers and frames; SLAM needs state estimation; navigation comes last. A cycle raises an error instead of an order. The graph is an illustrative example.
8. Real examples
- Example AMR: bring up drivers and check rates; publish the frame tree and verify with the transform tools; add the IMU filter and compare against odometry; run SLAM on a recorded bag; then close the loop with navigation, first in simulation, then at low speed in the test area.
9. Failure scenarios
- Navigation integrated before the frames were verified, so tuning chased a transform error.
- Every subsystem integrated in the same week.
- Exit criteria written as “works”.
- Missing stubs blocked a team for a month.
10. Troubleshooting
- If a step fails, return to the previous passed step and diff what changed.
- If a dependency is late, substitute a stub and mark the step’s result provisional.
- If the order contains a cycle, break it with an interface or a stub.
11. Validation
- The ordering example prints the levels above (checked by the site tests).
- Each step has measurable entry and exit criteria.
- Every exit result is recorded with date, version and data.
12. Engineering checklist
13. Further references
- NASA Systems Engineering Handbook, Rev 2 (2017): ntrs.nasa.gov/citations/20170001761, integration and verification processes, read 2026-11-05.